Back On July 14th 2024 we visited some model homes in Middleton Idaho and fell in love with the Agate floorplan that Hubble offered. It was a lot of money and we weren’t sure we wanted to buy just then, but they also had a lot we really liked. We talked about it on the drive home and called the sales agent leaving a message that we wanted it and let own agent know. We got a call back that the lot was already spoken for … long story short we ended up getting it when the other buyers backed out. These are pics of the progress as the house was being built. We visited almost every weekend from October to March when we finally closed. Even met some of the construction workers. The neighborhood turned out better than we could have hoped, our neighbors are awesome, and Middleton is the best city in Idaho to raise a family.
If you’re here and you’re not family you might be interested in the specs of the house. 6 bed, 3 bath, 3600sf on 1/3 acre. Hubble lets you semi-custom so we walled off the lot for another bedroom, turned an office into a bedroom, and walled off the dining room to make it an office. We declined their landscaping and decided to do the backyard ourselves, which we kind of regret. We have a nice weed hill going
August 26 2024
September 9 2024, still just dirt
October 4 2024, getting footings
October 20 2024
November 2 2024, start of framing and we missed them pouring the slab 🙁
November 6 2024, 2nd story framing
November 10 2024, whoa looks like a hoose and there’s a shower in the driveway
November 17 2024, windows are in
November 24th 2024, some electrical and hvac went in
December 4 2024, siding is on and drywall in the garage
December 8 2024, pre drywall inspection
My wife’s craft room
We wrote some notes on the sticks before they laid the bricks … I mean drywall
December 15 2024, house is drywalled
Dec 15 2024 interior drywall
Dec 22 2024 drywall mudding and joint compound, and garage doors
Dec 22 2024 the walls have texture
Jan 5 2025, welcome to the new year
Jan 12 2025
Jan 12 2025, a kitchen is born
Jan 19 2025, grandparents visiting
Jan 19 2025 flooring and counters
Jan 26 2025
Jan 26 2025 some carpet and trim. The rental we were living in had 0 carpet, we missed it.
Feb 2 2025 a bit of paint
Feb 2 2025 a fireplace
Feb 2 2025 Gracie’s happy place
Feb 2 2025
Feb 9 2025
Feb 21 2025, inspection – it passed
March 3 2025, final form and closing
March 7 2025, backyard is graded. We chose to do the backyard landscaping ourselves.
March 10 2025 moving in
March 10 2025 move in, girls were quick to unpack what’s important
March 13 2025 front landscaping done
March 13 2025, Lyta pups. We promised the kids a dog after we moved
Mar 20 beginning landscaping
March 20 still tillin
March 24 the sod is here
March 24 layin sod
March 25 we have lawn
March 26 God’s promise
April 9, God may have promised but I didn’t
April 13 a frog. We found a frog at our old house shortly after moving in too
April 15, trees n shrubs
April 16, my aspen grove
April 16 strawberry patch
April 18 a bird cam
April 19 fairy garden
April 21 hydrangea patch
April 30, built some planters
May 1, digging trenches for sprinklers
May 1 shovelin dirt
May 7 planters filled, Gracie’s garden started